Project-based development plan (vorhabenbezogener Bebauungsplan) · Decision to draw up the plan
Vorhabensbezogener BPlan Nr. 3 Zepelin Solarpark Zepelin
The development plan covers an area in the municipality of Zepelin, Landkreis Rostock. It is being drawn up (last known step: Decision to draw up the plan). The plan area covers about 179 hectares.
Not legally binding. Only the plan drawing in the Bauportal M-V (state building portal) is valid. View the plan drawing in the Bauportal Plan data: Bauportal M-V (state building portal), as of 13 October 2026. Sources and notes
At a glance
Details according to the Bauportal M-V, as of 13 October 2026
- Location
- Zepelin
- District
- Landkreis Rostock
Surveying in this region - Legal status
- In progress: Decision to draw up the plan
Decision to draw up the plan on 3 February 2022 - Type of plan
- Project-based development plan (vorhabenbezogener Bebauungsplan)
No. 3 - Area
- about 179 ha
- Plan documents
- View in the Bauportal M-V (in German)
Legal status
Can you build here?
Usually not yet under this development plan. The municipality is still drawing it up. The last known step is: Decision to draw up the plan. Until it comes into force, the law that applied before still decides what you may build. In some cases a project can be approved while the plan is still being drawn up (§ 33 BauGB).
When the development plan will come into force, and whether its content will still change until then, nobody can say for sure in advance.
What is a project-based development plan?
It applies to one specific project. A developer carries out the project according to a plan agreed with the municipality and commits to this in an implementation contract (Durchführungsvertrag, § 12 BauGB).
Which survey you need and when
For an energy facility in this area, you usually need these surveys.
-
To secure the land: land parcels and owners
We find out which land parcels the project touches and who owns them, from the real estate cadastre (Liegenschaftskataster) and the land register (Grundbuch). Surveying for wind and solar farms
-
For the planning: topographic survey plan
Boundaries, existing features and terrain, for large areas also as a terrain model from a drone flight.
-
For the permit: site plan
Whether it is a building application or an application under the Federal Immission Control Act (Bundes-Immissionsschutzgesetz): the site plan under BauVorlVO M-V is part of it, if needed with the documents for a public easement (Baulast), for example for an access road.
-
Before building starts: setting out
Foundations, fence, module rows, crane pads and access roads, on request during construction.
-
After completion: building survey and as-built records
Official survey where it is required, for example for wind turbines, plus an as-built plan and cable routes. Official building survey (Gebäudeeinmessung)
Building areas nearby
Other development plans and bylaws around this plan area, sorted by distance, each in its latest version.
-
BPlan Nr. 1 Zepelin OT Zepelin Hebammenacker
In force since 15 April 1993 600 m away
-
BPlan Nr. 1 Zepelin OT Oettelin Zepeliner Weg 1. Änderung
In force since 1 December 2021 1.0 km away 2 versions
-
Innenbereichssatzung Zepelin Klarstellungs und Ergänzungssatzung Zepelin
In force since 4 August 2022 1.0 km away
-
Aussenbereichssatzung Nr. 9 Gülzow-Prüzen OT Langensee
In force since 6 June 2019 2.0 km away Gülzow-Prüzen
-
BPlan Nr. 4 Bützow, Stadt Gewerbegebiet Tarnower Chaussee Südost 1. Änderung
In force since 7 October 1999 2.1 km away Stadt Bützow
-
BPlan Nr. 4., 5. Änderung, Bützow, Stadt "Gewerbegebiet Tarnower Chaussee, Südost"
In force since 4 June 2025 2.1 km away Stadt Bützow
-
BPlan Nr. 1 Bützow, Stadt Gewerbegebiet Tarnower Chaussee 10. Änderung
Adopted as a bylaw 2.1 km away Stadt Bützow 8 versions
-
Innenbereichssatzung Nr. 2/2 Gülzow-Prüzen OT Gülzow
In force since 8 November 2018 2.4 km away Gülzow-Prüzen
Where the information comes from
- Development plans and bylaws
- Bauportal Mecklenburg-Vorpommern (the state building portal). We copy the information published there into our database, last updated on 13 October 2026. View this plan in the Bauportal M-V (in German)
- Parcels
- Official real estate cadastre, © GeoBasis-DE/M-V. The map loads the parcels around the plan area directly from the state geodata server.
- Background maps
- basemap.de © GeoBasis-DE/BKG (CC BY 4.0), aerial photo © GeoBasis-DE/M-V.
Only the plan documents published by the municipality are legally binding. Our map is for guidance. If something has changed since the last update, it can differ from the Bauportal.
Are you planning to build in this area?
We tell you which survey you need and provide the site plan, setting out and official building survey from one office.