Project-based development plan (vorhabenbezogener Bebauungsplan) · In force
Vorhabensbezogener BPlan Nr. 14-I/95 Torgelow, Stadt Wohngebiet "Am Friedhof" 1. Änderung
The development plan covers an area in Stadt Torgelow, Landkreis Vorpommern-Greifswald. It has been in force since 14 October 2015. The plan area covers about 1,090 square metres.
Not legally binding. Only the plan drawing in the Bauportal M-V (state building portal) is valid. View the plan drawing in the Bauportal Plan data: Bauportal M-V (state building portal), as of 13 October 2026. Sources and notes
At a glance
Details according to the Bauportal M-V, as of 13 October 2026
- Location
- Stadt Torgelow
- District
- Vorpommern-Greifswald
Surveying in this region - Legal status
- In force since 14 October 2015
- Type of plan
- Project-based development plan (vorhabenbezogener Bebauungsplan)
No. 14-I/95 - Area
- about 1,090 m²
- Plan documents
- View in the Bauportal M-V (in German)
Legal status
Can you build here?
The development plan is legally binding. It sets out what may be built on the plots in its area. You find the details in the plan drawing and in the text part.
Whether your own project fits the plan is decided by the local building authority (untere Bauaufsichtsbehörde). You can ask them in advance with a preliminary building enquiry (Bauvoranfrage).
What is a project-based development plan?
It applies to one specific project. A developer carries out the project according to a plan agreed with the municipality and commits to this in an implementation contract (Durchführungsvertrag, § 12 BauGB).
Which survey you need and when
For a house in this area, you usually need these surveys.
-
Before you buy: clear up the boundaries
New plots are often created without boundary stones. Agree in the purchase contract who pays for forming the new land parcels and for the final boundary marking (Schlussabmarkung). Boundaries and plots
-
For the planning: topographic survey plan
The basis for your architect, with boundaries, heights and the rules of the plan (Lage- und Höhenplan). Topographic survey plan
-
For the building application: site plan
It is required by § 7 BauVorlVO M-V. If buildings or their spacing areas (Abstandsflächen) come closer than 0.5 m to the boundary, an official surveying body must make it, for example a publicly appointed surveying engineer (ÖbVI).
-
Before building starts: setting out
We transfer your project to the plot with rough and precise setting out and give the building company fixed height points. Surveying for your new house
-
After completion: official building survey
It is required by § 28 GeoVermG M-V. If we made the site plan and the setting out, the fee is 10 % lower. Official building survey (Gebäudeeinmessung)
All versions of this plan
The plan has been amended or extended. The latest version is shown first; each version has its own plan area and status.
-
Amendment no. 1, latest version (this page)
Vorhabensbezogener BPlan Nr. 14-I/95 Torgelow, Stadt Wohngebiet "Am Friedhof" 1. Änderung
In force since 14 October 2015 about 1,090 m²
-
Original version
Vorhabensbezogener BPlan Nr. 14-I/95 Torgelow, Stadt Wohngebiet "Am Friedhof"
In force since 3 April 1996 about 2.0 ha
Building areas nearby
Other development plans and bylaws around this plan area, sorted by distance, each in its latest version.
-
BPlan Nr. 41/2021 Torgelow, Stadt "Muckerwitzweg"
In force since 16 July 2022 under 100 m away
-
BPlan Nr. 45/2023 Torgelow, Stadt Erweiterung Fabrikstraße
In progress: Draft 700 m away
-
BPlan Nr. 35/09 Torgelow, Stadt "Neuordnung Wiesenstraße/Fabrikstraße"
In force since 1 July 2010 700 m away
-
BPlan Nr. 33/07 Torgelow, Stadt "Lindenstraße"
In force since 18 June 2008 800 m away
-
BPlan Nr. 44/2022 Torgelow, Stadt "Stellplatzanlage Lindenstraße"
In force since 22 August 2026 800 m away
-
BPlan Nr. 30/05 Torgelow, Stadt "Wohngebiet Südliche Ueckerstraße" 1. Änderung
In force since 20 June 2007 1.1 km away 2 versions
-
BPlan Nr. 24/02 Torgelow, Stadt Wohnbebauung "Südliche Borkenstraße"
In force since 14 January 2004 1.1 km away
-
BPlan Nr. 39/19 Torgelow, Stadt "Photovoltaikanlage Rudolf-Diesel-Straße"
In force since 18 October 2019 1.2 km away
Where the information comes from
- Development plans and bylaws
- Bauportal Mecklenburg-Vorpommern (the state building portal). We copy the information published there into our database, last updated on 13 October 2026. View this plan in the Bauportal M-V (in German)
- Parcels
- Official real estate cadastre, © GeoBasis-DE/M-V. The map loads the parcels around the plan area directly from the state geodata server.
- Background maps
- basemap.de © GeoBasis-DE/BKG (CC BY 4.0), aerial photo © GeoBasis-DE/M-V.
Only the plan documents published by the municipality are legally binding. Our map is for guidance. If something has changed since the last update, it can differ from the Bauportal.
Are you planning to build in this area?
We tell you which survey you need and provide the site plan, setting out and official building survey from one office.