Qualified development plan (qualifizierter Bebauungsplan) · In force
BPlan Nr. 3 Wusterhusen Sondergebiet Windenergiepark 1. Änderung
The development plan covers an area in the municipality of Wusterhusen, Landkreis Vorpommern-Greifswald. It has been in force since 30 January 2017. The plan area covers about 204 hectares.
Not legally binding. Only the plan drawing in the Bauportal M-V (state building portal) is valid. View the plan drawing in the Bauportal Plan data: Bauportal M-V (state building portal), as of 13 October 2026. Sources and notes
At a glance
Details according to the Bauportal M-V, as of 13 October 2026
- Location
- Wusterhusen
- District
- Vorpommern-Greifswald
Surveying in this region - Legal status
- In force since 30 January 2017
- Type of plan
- Qualified development plan (qualifizierter Bebauungsplan)
No. 3 - Area
- about 204 ha
- Plan documents
- View in the Bauportal M-V (in German)
Legal status
Can you build here?
The development plan is legally binding. It sets out what may be built on the plots in its area. You find the details in the plan drawing and in the text part.
Whether your own project fits the plan is decided by the local building authority (untere Bauaufsichtsbehörde). You can ask them in advance with a preliminary building enquiry (Bauvoranfrage).
What is a qualified development plan?
It sets at least the type and extent of building use, the parts of the plots that may be built on and the local roads and paths. A project is allowed if it does not go against these rules and access and services are secured (§ 30 Abs. 1 BauGB).
Which survey you need and when
For an energy facility in this area, you usually need these surveys.
-
To secure the land: land parcels and owners
We find out which land parcels the project touches and who owns them, from the real estate cadastre (Liegenschaftskataster) and the land register (Grundbuch). Surveying for wind and solar farms
-
For the planning: topographic survey plan
Boundaries, existing features and terrain, for large areas also as a terrain model from a drone flight.
-
For the permit: site plan
Whether it is a building application or an application under the Federal Immission Control Act (Bundes-Immissionsschutzgesetz): the site plan under BauVorlVO M-V is part of it, if needed with the documents for a public easement (Baulast), for example for an access road.
-
Before building starts: setting out
Foundations, fence, module rows, crane pads and access roads, on request during construction.
-
After completion: building survey and as-built records
Official survey where it is required, for example for wind turbines, plus an as-built plan and cable routes. Official building survey (Gebäudeeinmessung)
All versions of this plan
The plan has been amended or extended. The latest version is shown first; each version has its own plan area and status.
-
Amendment no. 1, latest version (this page)
BPlan Nr. 3 Wusterhusen Sondergebiet Windenergiepark 1. Änderung
In force since 30 January 2017 about 204 ha
-
Original version
BPlan Nr. 3 Wusterhusen Sondergebiet Windenergiepark
In force since 6 May 1998 about 208 ha
Building areas nearby
Other development plans and bylaws around this plan area, sorted by distance, each in its latest version.
-
BPlan Nr. 4 Wusterhusen Erweiterung Firmengelände HAB Service- und Verwaltungsgesellschaft mbH
In progress: Consultation of authorities 750 m away
-
BPlan Nr. 9 Brünzow OT Kräpelin Erweiterung des Firmengeländes HAB
In progress: Draft 800 m away Brünzow
-
In progress: Decision to draw up the plan 1.5 km away Brünzow
-
BPlan Nr. 6 Wusterhusen „Zentrale Wohnbebauung mit Parkanlage im Ortsteil Konerow“
In progress: Decision to draw up the plan 1.7 km away
-
BPlan Nr. 1 Wusterhusen OT Wusterhusen Reines Wohngebiet Nord 2. Änderung
In force since 16 August 2013 1.7 km away 2 versions
-
BPlan Nr. 7 Wusterhusen "Solarpark Wusterhusen zwischen Konerow und Pritzwald"
In progress: Draft 2.2 km away
-
BPlan Nr. 1 Lubmin, Seebad Nördlich L 40 6. Änderung
In force 2.9 km away Seebad Lubmin 3 versions
-
BPlan Nr. 12 Lubmin, Seebad Wohngebiet Altes Dorf 1
In force since 24 May 2018 2.9 km away Seebad Lubmin
Where the information comes from
- Development plans and bylaws
- Bauportal Mecklenburg-Vorpommern (the state building portal). We copy the information published there into our database, last updated on 13 October 2026. View this plan in the Bauportal M-V (in German)
- Parcels
- Official real estate cadastre, © GeoBasis-DE/M-V. The map loads the parcels around the plan area directly from the state geodata server.
- Background maps
- basemap.de © GeoBasis-DE/BKG (CC BY 4.0), aerial photo © GeoBasis-DE/M-V.
Only the plan documents published by the municipality are legally binding. Our map is for guidance. If something has changed since the last update, it can differ from the Bauportal.
Are you planning to build in this area?
We tell you which survey you need and provide the site plan, setting out and official building survey from one office.