Qualified development plan (qualifizierter Bebauungsplan) · In force
BPlan Nr. 9 Saal OT Saal, Alte Ziegelei
The development plan covers an area in the municipality of Saal, Landkreis Vorpommern-Rügen. It has been in force since 11 March 2013. The plan area covers about 2.7 hectares.
There is a newer version: Amendment no. 2, In progress: Decision to draw up the plan
Not legally binding. Only the plan drawing in the Bauportal M-V (state building portal) is valid. View the plan drawing in the Bauportal Plan data: Bauportal M-V (state building portal), as of 13 October 2026. Sources and notes
At a glance
Details according to the Bauportal M-V, as of 13 October 2026
- Location
- Saal
- District
- Vorpommern-Rügen
Surveying in this region - Legal status
- In force since 11 March 2013
- Type of plan
- Qualified development plan (qualifizierter Bebauungsplan)
No. 9 - Area
- about 2.7 ha
- Plan documents
- View in the Bauportal M-V (in German)
Legal status
Can you build here?
The development plan is legally binding. It sets out what may be built on the plots in its area. You find the details in the plan drawing and in the text part.
Whether your own project fits the plan is decided by the local building authority (untere Bauaufsichtsbehörde). You can ask them in advance with a preliminary building enquiry (Bauvoranfrage).
What is a qualified development plan?
It sets at least the type and extent of building use, the parts of the plots that may be built on and the local roads and paths. A project is allowed if it does not go against these rules and access and services are secured (§ 30 Abs. 1 BauGB).
Which survey you need and when
For a building project in this area, you usually need these surveys.
-
Before you buy: clear up the boundaries
New plots are often created without boundary stones. Agree in the purchase contract who pays for forming the new land parcels and for the final boundary marking (Schlussabmarkung). Boundaries and plots
-
For the planning: topographic survey plan
The basis for your architect, with boundaries, heights and the rules of the plan (Lage- und Höhenplan). Topographic survey plan
-
For the building application: site plan
It is required by § 7 BauVorlVO M-V. If buildings or their spacing areas (Abstandsflächen) come closer than 0.5 m to the boundary, an official surveying body must make it, for example a publicly appointed surveying engineer (ÖbVI).
-
Before building starts: setting out
We transfer your project to the plot with rough and precise setting out and give the building company fixed height points. Surveying for your new house
-
After completion: official building survey
It is required by § 28 GeoVermG M-V. If we made the site plan and the setting out, the fee is 10 % lower. Official building survey (Gebäudeeinmessung)
All versions of this plan
The plan has been amended or extended. The latest version is shown first; each version has its own plan area and status.
-
Amendment no. 2, latest version
BPlan Nr. 9 Saal OT Saal, Alte Ziegelei, 2. Änderung
In progress: Decision to draw up the plan about 2,380 m²
-
Amendment no. 1
BPlan Nr. 9 Saal OT Saal, Alte Ziegelei, 1. Änderung
In force since 19 September 2019 about 2.7 ha
-
Original version (this page)
BPlan Nr. 9 Saal OT Saal, Alte Ziegelei
In force since 11 March 2013 about 2.7 ha
Building areas nearby
Other development plans and bylaws around this plan area, sorted by distance, each in its latest version.
-
BPlan Nr. 12 Saal OT Saal, Neubau Kita und Wohnen
In progress: Decision to draw up the plan 400 m away
-
Innenbereichssatzung Saal OT Saal, Im nördlichen Kreuzungsbereich der Gartenstraße und Lange Straße
In force since 3 November 2024 750 m away
-
BPlan Nr. 5 Saal OT Saal, Wassersport
In force since 3 November 2016 1.5 km away
-
BPlan Nr. 6 Saal OT Kückenshagen, Biogasanlage Kückenshagen
In force since 18 July 2008 1.6 km away
-
BPlan Nr. 32 Ribnitz-Damgarten, Bernsteinstadt OT Langendamm Wohnhausbebauung Heideweg 1. Ergänzung
In force since 6 November 2012 2.6 km away Bernsteinstadt Ribnitz-Damgarten 2 versions
-
BPlan Nr. 66 Ribnitz-Damgarten, Bernsteinstadt OT Langendamm Wohnbebauung Wasserreihe Ost
In force since 22 November 2011 2.7 km away Bernsteinstadt Ribnitz-Damgarten
-
In progress: Draft 2.7 km away
-
Innenbereichssatzung Nr. 2 Saal OT Hessenburg, Nordwest
In force since 25 November 2011 2.8 km away
Where the information comes from
- Development plans and bylaws
- Bauportal Mecklenburg-Vorpommern (the state building portal). We copy the information published there into our database, last updated on 13 October 2026. View this plan in the Bauportal M-V (in German)
- Parcels
- Official real estate cadastre, © GeoBasis-DE/M-V. The map loads the parcels around the plan area directly from the state geodata server.
- Background maps
- basemap.de © GeoBasis-DE/BKG (CC BY 4.0), aerial photo © GeoBasis-DE/M-V.
Only the plan documents published by the municipality are legally binding. Our map is for guidance. If something has changed since the last update, it can differ from the Bauportal.
Are you planning to build in this area?
We tell you which survey you need and provide the site plan, setting out and official building survey from one office.